Question 21

Which agile concept involves estimating the relative level of effort needed to complete a user story using abstract units called story points?

a) Story prioritization
b) Story estimation
c) Sprint velocity
d) Planning poker

Correct Answer: b) Story estimation

Explanation: Story estimation involves assigning story points to user stories based on the relative level of effort required to complete them.

Question 22

Which project role is responsible for ensuring the team has the tools and environment needed to succeed and removing any impediments to progress?

a) Scrum master
b) Product owner
c) Project sponsor
d) Business analyst

Correct Answer: a) Scrum master

Explanation: The Scrum master ensures that the team has the tools and environment needed to succeed and works to remove any impediments to progress.

Question 23

Which chart is used to analyze how often certain issues occur, typically to prioritize problem-solving efforts in quality management?

a) Fishbone diagram
b) Pareto chart
c) Gantt chart
d) Control chart

Correct Answer: b) Pareto chart

Explanation: A Pareto chart is used to prioritize problem-solving efforts by analyzing how often certain issues occur, helping teams focus on the most frequent issues.

Question 24

Which project document tracks high-level progress and provides regular updates to stakeholders on the project’s status?

a) Project charter
b) Risk register
c) Status report
d) Change log

Correct Answer: c) Status report

Explanation: The status report provides high-level progress updates to stakeholders, summarizing the project’s current status.

Question 25

What is the main benefit of using a Program Evaluation and Review Technique (PERT) chart in project management?

a) It shows the project’s duration and critical path
b) It shows the frequency of project issues
c) It tracks resource usage over time
d) It evaluates project performance

Correct Answer: a) It shows the project’s duration and critical path

Explanation: A PERT chart shows the project’s tasks, duration, and critical path, helping project managers identify the most time-consuming activities.

Question 26

Which risk response strategy focuses on reducing the probability or impact of a risk without eliminating it entirely?

a) Avoid
b) Transfer
c) Mitigate
d) Accept

Correct Answer: c) Mitigate

Explanation: Mitigating a risk involves reducing its probability or impact to make it more manageable without eliminating it entirely.

Question 27

Which meeting type focuses on making decisions and gathering support for the chosen actions but doesn’t aim to resolve issues immediately?

a) Informative meeting
b) Collaborative meeting
c) Decisive meeting
d) Task-setting meeting

Correct Answer: c) Decisive meeting

Explanation: Decisive meetings focus on exchanging information, making decisions, and building support for chosen actions but don’t focus on issue resolution.

Question 28

What is the purpose of a sprint retrospective in the Scrum framework?

a) To prioritize the product backlog
b) To plan the next sprint
c) To reflect on the sprint and identify improvements
d) To demonstrate the completed work to stakeholders

Correct Answer: c) To reflect on the sprint and identify improvements

Explanation: A sprint retrospective is held at the end of a sprint to reflect on the team’s work and identify areas for improvement in future sprints.

Question 29

Which project management tool visually displays the relationship between two variables to help identify trends and correlations?

a) Scatter diagram
b) Gantt chart
c) Histogram
d) Fishbone diagram

Correct Answer: a) Scatter diagram

Explanation: A scatter diagram visually displays the relationship between two variables, helping identify trends and correlations between them.

Question 30

What type of organizational structure is designed around projects, with no permanent departments, and where project managers have full control?

a) Functional organization
b) Matrix organization
c) Projectized organization
d) Hybrid organization

Correct Answer: c) Projectized organization

Explanation: A projectized organization is structured entirely around projects, where project managers have full control over resources and project execution.

Question 31

Which tool is often used in agile frameworks to visually track the progress of tasks as they move through different stages of completion?

a) Gantt chart
b) Burnup chart
c) Kanban board
d) Control chart

Correct Answer: c) Kanban board

Explanation: A Kanban board is used in agile frameworks to visually track the progress of tasks as they move through different stages of completion.

Question 32

Which contract type involves both a fixed price for the project and the possibility of an additional financial incentive if specific targets are met?

a) Firm Fixed Price (FFP)
b) Time and Material (T&M)
c) Fixed Price Incentive Fee (FPIF)
d) Cost Plus Fixed Fee (CPFF)

Correct Answer: c) Fixed Price Incentive Fee (FPIF)

Explanation: A Fixed Price Incentive Fee (FPIF) contract includes a fixed price for the project and provides additional incentives for meeting specific targets.

Question 33

Which agile role is responsible for setting the vision for the product and prioritizing the product backlog based on customer needs?

a) Scrum master
b) Project manager
c) Product owner
d) Team lead

Correct Answer: c) Product owner

Explanation: The product owner is responsible for setting the product vision and prioritizing the product backlog to ensure alignment with customer needs.

Question 34

Which risk response strategy involves taking no proactive action and accepting the consequences of a risk if it occurs?

a) Avoid
b) Accept
c) Transfer
d) Mitigate

Correct Answer: b) Accept

Explanation: The accept strategy involves taking no proactive action and accepting the consequences if the risk materializes.

Question 35

Which project management process involves collecting information on project performance and comparing it to the project plan?

a) Quality assurance
b) Performance reporting
c) Control monitoring
d) Scope management

Correct Answer: b) Performance reporting

Explanation: Performance reporting involves collecting information on project performance and comparing it to the project plan to ensure objectives are being met.

Question 36

What tool is used to measure how much of a project’s budget has been spent and how much remains over time?

a) Project dashboard
b) Budget burndown chart
c) Gantt chart
d) Control chart

Correct Answer: b) Budget burndown chart

Explanation: A budget burndown chart tracks how much of a project’s budget has been spent and how much remains over time, providing a visual representation of financial progress.

Question 37

Which testing method runs a basic check to confirm that the most essential functions of a system work, before more detailed testing is conducted?

a) Smoke testing
b) Regression testing
c) Stress testing
d) User acceptance testing

Correct Answer: a) Smoke testing

Explanation: Smoke testing runs a basic check to confirm that the system’s most essential functions work properly before more detailed testing takes place.

Question 38

What project role is typically responsible for conducting risk assessments and identifying ways to mitigate risks?

a) Product owner
b) Risk manager
c) Project sponsor
d) Project manager

Correct Answer: d) Project manager

Explanation: The project manager is typically responsible for conducting risk assessments and developing strategies to mitigate risks.

Question 39

What does a Work Breakdown Structure (WBS) provide in project management?

a) A detailed project schedule
b) A decomposition of project scope into smaller deliverables
c) A list of project risks
d) A project timeline with major milestones

Correct Answer: b) A decomposition of project scope into smaller deliverables

Explanation: A Work Breakdown Structure (WBS) provides a hierarchical decomposition of the project scope into smaller, manageable deliverables.

Question 40

What is the primary purpose of a project kickoff meeting?

a) To present the project budget
b) To introduce the project team and align everyone with project goals
c) To review completed tasks
d) To develop the project scope

Correct Answer: b) To introduce the project team and align everyone with project goals

Explanation: A project kickoff meeting introduces the project team, aligns stakeholders, and sets expectations for the project’s objectives and goals.