Question 41

What method is used to estimate project costs by breaking down the work into smaller components and aggregating the cost estimates for each?

a) Parametric estimating
b) Analogous estimating
c) Bottom-up estimating
d) Three-point estimating

Correct Answer: c) Bottom-up estimating

Explanation: Bottom-up estimating breaks down the work into smaller components and aggregates the cost estimates for each, providing a more detailed estimation.

Question 42

Which project document provides stakeholders with a summary of project progress and is distributed according to the communication plan?

a) Change log
b) Status report
c) Issue log
d) Risk register

Correct Answer: b) Status report

Explanation: The status report summarizes project progress and is distributed to stakeholders according to the project's communication plan.

Question 43

 Which role is responsible for facilitating communication within a Scrum team and removing any obstacles that prevent the team from delivering on its goals?

a) Product owner
b) Scrum master
c) Project sponsor
d) Business analyst

Correct Answer: b) Scrum master

Explanation: The Scrum master facilitates communication and removes obstacles that prevent the team from delivering on its goals.

Question 44

What agile document contains a prioritized list of features and user stories that the development team will work on in future sprints?

a) Sprint backlog
b) Product backlog
c) Burndown chart
d) Release plan

Correct Answer: b) Product backlog

Explanation: The product backlog contains a prioritized list of features and user stories that the development team will work on in future sprints.

Question 45

Which diagram is used to identify potential causes of a problem and is also known as a cause-and-effect or Ishikawa diagram?

a) Fishbone diagram
b) Pareto chart
c) Control chart
d) Run chart

Correct Answer: a) Fishbone diagram

Explanation: A fishbone diagram, also known as an Ishikawa diagram, is used to identify potential causes of a problem.

Question 46

Which testing method is typically conducted by end-users before formally accepting a system for production use?

a) Smoke testing
b) Unit testing
c) User acceptance testing (UAT)
d) Stress testing

Correct Answer: c) User acceptance testing (UAT)

Explanation: User acceptance testing (UAT) is conducted by end-users before formally accepting a system for production use, ensuring it meets their needs.

Question 47

What type of matrix organizational structure emphasizes project work over functional duties and gives the project manager more authority?

a) Weak matrix
b) Balanced matrix
c) Strong matrix
d) Functional

Correct Answer: c) Strong matrix

Explanation: A strong matrix organizational structure emphasizes project work over functional duties, giving the project manager greater authority over resources.

Question 48

 Which project management process involves regularly tracking project risks and updating the risk register as needed?

a) Risk identification
b) Risk mitigation
c) Risk monitoring
d) Risk transfer

Correct Answer: c) Risk monitoring

Explanation: Risk monitoring involves regularly tracking project risks and updating the risk register to ensure that risks are managed effectively throughout the project.

Question 49

Which tool visually tracks the status of tasks and their progress across various stages of completion in an agile framework?

a) Sprint backlog
b) Gantt chart
c) Kanban board
d) Milestone chart

Correct Answer: c) Kanban board

Explanation: A Kanban board visually tracks the status of tasks and their progress across different stages of completion, making it easier to manage workflow.

Question 50

Which contract type allows the seller to be reimbursed for allowable costs, plus a fixed fee regardless of project outcomes?

a) Firm Fixed Price (FFP)
b) Cost Plus Fixed Fee (CPFF)
c) Time and Material (T&M)
d) Fixed Price Incentive Fee (FPIF)

Correct Answer: b) Cost Plus Fixed Fee (CPFF)

Explanation: A CPFF contract reimburses the seller for allowable costs plus a fixed fee, regardless of project performance or outcomes.

 